Situated on a steep hillside overlooking Kelburn Viaduct, Party Wall comprises two modest-sized homes beneath a single roof.

Designed by Patchwork Architecture in collaboration with structural engineers Spencer Holmes, the dwellings are cleverly joined together and separated by the central concrete core. This three-storey in-situ concrete wall incorporates internal staircases and storage while anchoring the building to the hillside.

The project was completed in 2021 during Dorset Construction's time operating in Wellington.

THE CONSTRUCTION

The scale and complexity of the in-situ concrete work were unusual for a residential project, particularly on a steep site with limited access. A considerable amount of planning went into the formwork, with timber floors constructed progressively to provide access to the next stages of concrete work.

Working alongside Patchwork Architecture, the team developed a colour-coded 3D model to carefully plan the sequence of concrete pours. With the concrete itself forming the finished surface, there was very little room for error.

Internally, the concrete sits comfortably alongside the cedar linings.

RECOGNITION

In 2022, Patchwork Architecture received the Sir Ian Athfield Award for Housing for Party Wall, one of New Zealand's highest architectural honours.

In-situ concrete house Wellington NZ